How do you calculate wall plastering?
Based on the specified kind of mixture and plaster thickness, multiply your area with the corresponding values from the plaster proportion table:
- Quantity of Cement Bags = Area * Cement multiplier for a Class “B” mix.
- = 1.152 bags ~ 2 bags.
- Quantity of Sand = Area * Sand multiplier for a Class “B” mix.
- = 0.096 m3
How do you calculate plastering of a house?
Area of Plastering = Length × Width. Amount of Cement = [(Dry Volume × Cement Ratio) ÷ Sum of Ratio] ÷ Volume of Cement. Amount of Sand = [(Dry Volume × Cement Ratio) ÷ Sum of Ratio] × Density of Sand.
What is the ratio of plaster?
Different ratios of Cement mortar used for plastering are tabulated below:
Mix Ratio | Areas of usage |
---|---|
1:4 | Used for Ceiling and external walls |
1:3 | As its a rich mortar mix and it is used where external walls are prone to severe climatic conditions. It is also used for repair works. |
What is the mix ratio for plastering?
Plaster Mix Ratio Mix cement and sand in the ratio of 1:6 (1 cement:6 sand) for inner plastering of bricks. And for outer plastering mix it in the ratio of 1:4. On a brick wall never do plastering of thickness more than 12 or 15mm.
How do you calculate the area of a plaster?
Step 1: Calculate the Area of Plastering
- Step 1: Calculate the Area of Plastering. Area = width x height = 10 x 10 = 100m2 Step 2: Find the Volume of Plastering.
- Step 2: Find the Volume of Plastering. Volume of First Coat = Area of Plastering x Thickness of Plastering. = 100m2 x 12mm (Convert mm to m)
What is the rate for plastering?
Wall Plaster Cost For 1000, 2000, 3000,4000, & 5000 sq. ft area
Description | Rate Per sq.ft | 1000 sq.ft |
---|---|---|
Wall Plaster Labour Rs.25/- per sq.ft | Rs.25/-* | Rs.25,000 |
Material Cost (Plastering M-Sand, Cement) – Rs.35/- per sq.ft | Rs.35/-* | Rs.35,000 |
Total Cost of Wall Plaster Rs.60/- per sq.ft | Rs.60/-* | Rs.60,000/-* |
What is the ratio of cement plaster?
6 MM thickness of cement plaster and cement mortar 1:3 or 1:4 is recommended for cement plastering on RCC surfaces, on the RCC walls, Fascia etc. or as directed by the Engineer, 6 MM to 10 MM thickness of cement plaster and cement mortar in 1:3 or 1:4 ratios is recommended for underside of RCC slabs.
How much sand do I need for 1 square meter plaster?
Ans :- 34.5 Kgs (0.02128 m3) sand and 0.154 bags (7.7 Kgs) cement required per square metre for plastering in 20mm thick plaster 1:4. Sand required for 1 sqm plastering:- sand requirement depend on thickness of plastering, around 21kgs to 34kgs sand required for 1 sqm plastering.
What is the thickness of plastering?
Cement plaster is generally used with 13 mm thickness and sometimes it can be of 19 mm thickness also. 19 mm plaster is done in two parts. First layer is of 13 mm and 2nd is of 6 mm thickness.
How many square meters of plastering can 1 Mason a day?
ft~12.00sq. m per day. In high rise buildings the plastering out put will decrease with increasing height of floor on which the mason has to work due to the wind, personal safety considerations and the weather . Here usually an output of about 60sq.